Pre-subscription phase
Stadtwerke Kempen GmbH – a wholly owned subsidiary of the city of Kempen – offers investors the opportunity to participate in the crowdfunding project “Large-scale battery storage in Kempen” and to contribute to the development of a future-oriented energy infrastructure.
The subscription phase is divided into two stages:
Exclusive pre-subscription phase:
Customers (with an electricity, district heating or gas contract) of Stadtwerke Kempen GmbH have the opportunity to participate early in the crowdfunding via profit participation rights (Genussrechte) from 03.08.2026 up to and including 17.08.2026.Public subscription phase:
From 18.08.2026, the crowdfunding is open to all investors across Germany. The subscription phase ends when the funding target is reached, but no later than 31.10.2026.
Welcome note

Dear investors,
Stadtwerke Kempen GmbH – a wholly owned subsidiary of the city of Kempen – is pleased to present our new project “Large-scale battery storage in Kempen”.
As a modern municipal energy company, we actively shape the energy transition locally. The expansion of renewable energy, in particular wind power and photovoltaic systems, is leading to ever greater fluctuations on electricity markets across Germany. Periods with very low or even negative electricity prices are noticeably increasing. At the same time, the need for flexible solutions to stabilise electricity grids is growing.
This is exactly where our project comes in: with the large-scale battery storage system, we are creating the opportunity to temporarily store surplus electricity from renewable energy and then make it available when it is needed. For example, electricity can be stored in periods of low prices and fed back into the grid when demand is higher.
In this way, we not only make an important contribution to security of supply and grid stability, but also support the efficient use of renewable energy and the achievement of climate targets.
With this project, we are taking the next step towards a sustainable energy future – and would like you to participate. Together with you, we want to realise the large-scale battery storage system on our power plant site and actively advance the energy transition in Kempen.
Our investment offer combines ecological responsibility with an economic perspective. We look forward to taking this path together with you.
Daniel Banzhaf
Managing Director, Stadtwerke Kempen GmbH
Opportunities and risks
| Opportunities | Risks |
|---|---|
|
|
Participating in the crowdfunding project “Large-scale battery storage in Kempen” is an investment in the sustainable energy future of the city of Kempen. The steady expansion of wind and photovoltaic systems is increasing the need for storage and flexibility solutions to integrate renewable energy into the electricity system.
The planned large-scale battery storage system makes it possible to temporarily store surplus electricity from renewable energy and make it available again at a later time. This means that more renewable electricity can be used, electricity grids can be relieved and security of supply can be strengthened.
With the construction and commissioning of a 2.5 MW large-scale battery storage system, Stadtwerke Kempen is consistently advancing the local energy transition.
The site is located on the existing power plant grounds at Otto-Schott-Straße in Kempen. The required grid connections and feed-in and withdrawal capacities are already in place there. The necessary permits were granted in 2025. The battery storage system was procured through a tendering procedure and delivered to Kempen in April 2026.
In the coming months, it will be connected to the electricity grid and technically and commercially commissioned for the energy market. The start of marketing is planned for summer 2026.

Use of funds
As part of the project “Large-scale battery storage in Kempen”, a 2.5 MW large-scale battery storage system will be built and commissioned with an investment volume of 1.4 million €.
The storage system serves to provide flexibility in the electricity market, to better integrate renewable energy and to stabilise the electricity grid. By marketing the storage capacity, additional market opportunities are to be exploited.
Commissioning of the battery storage system is planned for summer 2026.
Sources of funds – financing structure

Project company
Stadtwerke Kempen GmbH is a wholly owned subsidiary of the city of Kempen and is entirely in municipal ownership. As a regionally rooted energy supply company, we have for many years stood for a safe, reliable and sustainable supply of electricity, gas, district heating, renewable energy services (storage, PV, heat pumps, etc.) and water. In addition, we operate the water world and sauna AquaSol.
The energy transition and Germany’s climate protection targets increasingly shape the future direction of our company. We see the transformation of the energy market not only as a social responsibility, but also as an opportunity to develop our infrastructure and services sustainably.
With the project “Large-scale battery storage in Kempen”, we are investing specifically in a modern storage technology to stabilise electricity grids and make better use of renewable energy. In implementing it, security of supply, environmental compatibility and economic viability are our main priorities.
The sustainable further development of our products and infrastructure strengthens the long-term competitiveness and future viability of Stadtwerke Kempen and its subsidiaries.
Organisation chart

Customers of Stadtwerke Kempen as well as interested investors have the opportunity to participate in the project “Large-scale battery storage in Kempen” via DKB-Crowd. The financing takes the form of profit participation rights (Genussrechte) with qualified subordination, with a total volume of 1,400,000 €.
In the first investment phase, the offer is exclusively aimed at customers of Stadtwerke Kempen GmbH. The opportunity to participate will then be opened up to residents of Kempen and to people across Germany.
The interest rate is 4.4% per year. In addition, if the company has a corresponding annual surplus, a profit-related bonus of up to 1.0% per year may be paid out. The term of the investment (Vermögensanlage) is 10 years. Repayment is made in equal instalments in annual partial amounts from 2027.
No arrangement fees are charged to investors. Liability is limited to the respective investment amount.
Your investment options at a glance
Investment volume: 1,400,000 €
Exclusive pre-subscription phase for customers of Stadtwerke Kempen:
03.08.2026 to 17.08.2026Public investment phase:
18.08.2026 to 31.10.2026 or until the funding target is reachedInterest:
4.4% p.a.
plus up to 1.0% p.a. profit-related bonus
Minimum investment: 500 €
(investment amounts in steps of 100 €)Maximum investment: 25,000 €
Term: 10 years
Interest payment: annually on 30.09., first on 30.09.2027
Form of investment: profit participation rights (Genussrechte) with qualified subordination
Repayment: annually, 10% of the investment amount from 2027 to 2036
Arrangement fees: none


| Term | Interest | Repayment | Interest date | Maturity |
|---|---|---|---|---|
| 10 years | 4.40 % p. a. | in equal instalments | 30.09. annually (first on 30.09.2027) | 31.12.2036 |
| Type of loan | in equal instalments |
|---|---|
| Interest payment frequency | annually |
| Available from | 03.08.2026 |
| Minimum investment | EUR 500 |
| Maximum investment | EUR 25,000 |
Downloads
Your personal payment plan (4.40 % interest p. a.)
| Year | Date | Payment (gross) | Interest | Repayment | Status |
|---|