- Sustainability
- Regional focus
- Agricultural use
Welcome note
Dear residents of Obersöchering and the surrounding area,
A future-proof energy supply needs sufficient renewable electricity locally. For this reason, 17er Oberlandenergie GmbH, ESB Erneuerbare Energien GmbH and the landowner have joined forces on a shared project for regional solar power generation.
In the municipality of Obersöchering, near Abertshausen, we have found an ideal site for our solar park. High-efficiency solar modules with a total capacity of approx. 4.5 megawatt peak (MWp) will be installed on the plot of just under 4.2 hectares.
The solar park stands out for its innovative approach: it combines the generation of electricity from renewable energy with agricultural use. Thanks to the elevated mounting of the modules, the land can continue to be used as pasture for cattle from the landowner's herd.
You, too, as a resident, can become an important part of the project! Take part in our solar park through a subordinated loan with an attractive rate of interest. Together, we are taking a big step towards the energy transition in the region.
We would be delighted to welcome you to our energy transition team!
Kind regards
Your Solarpark Abertshausen team
Contribution to the UN Sustainable Development Goals
Production of renewable electricity from solar energy, fed into the public electricity grid
Cooperation with partners in the region
Investment in regional energy infrastructure with innovative dual use through agri-PV
Construction of a PV park on site and supply of the region with renewably generated electricity
Continuation of agricultural use alongside renewable electricity generation
Permanent CO2 savings through electricity production from a renewable energy source, and enhancement of the land through extensive farming
Cooperation with regional partners in the financing, construction and subsequent operation of the plant
Opportunities and risks
| Opportunities | Risks |
|---|---|
|
|
Together with the landowner, 17er Oberlandenergie GmbH and ESB Erneuerbare Energien GmbH are taking a big step towards the energy transition for the municipality of Obersöchering and the Oberland region. For this purpose, a solar park will be built as an agri-PV plant on a plot of just under 4.2 hectares. Regional value creation is a central concern for the project partners, which is why local stakeholders are involved throughout the project.
The planned installed module capacity is around 4.5 MWp. This results in annual feed-in to the local electricity grid of up to 5.2 million kilowatt hours (kWh). This corresponds to about 70% of the annual electricity demand of the municipality of Obersöchering – or the demand of approx. 1,700 three-person households.
As an agri-PV plant, the solar park preserves the land for agriculture. The modules will be mounted particularly high so that cattle can graze both beneath and between the module rows.
In August 2025, the project was awarded a contract in the tender based on the Renewable Energy Sources Act (Erneuerbare-Energien-Gesetz, EEG) – this gives the project planning certainty in the form of a minimum revenue for the electricity fed in over 20 years. In addition to the EEG remuneration, the planned marketing of the electricity generated by the shareholders will contribute to the profitability of the project.
Construction work on site is largely complete, so the solar park will be commissioned in good time for summer 2026.
Use of funds
The citizen capital raised will be used by the project to build the agri-PV plant.
Source of funds – financing structure
The cost of the plant amounts to around 2.75 million euros. The shareholders are contributing a total of 827,000 euros as equity. In addition, local residents have the opportunity to participate financially in the form of a qualified subordinated loan with a total volume of 250,000 euros. The remaining part of the project financing is provided by Sparkasse Oberland.

Project company
Solarpark Abertshausen is a joint venture between the regional project partners 17er Oberlandenergie GmbH and ESB Erneuerbare Energien GmbH, and the landowner.
17er Oberlandenergie GmbH is a regional association of six municipal utilities and more than 40 other municipalities in the Oberland region.
ESB Erneuerbare Energien GmbH is a 100% subsidiary of Energie Südbayern GmbH, a municipally rooted energy supplier and service provider with expertise built over more than 60 years of company history.
By building the solar park, the project company is actively helping to shape the energy transition locally. At the same time, land remains available for local agriculture and regional value creation is strengthened.
A strong community that champions clean energy for the climate and brings it into harmony with agricultural land use.
Organisation chart

Residents have the opportunity to participate in the solar park via DKB Crowd by means of a qualified subordinated loan totalling 250,000 euros.
Residents whose main place of residence is in the municipalities of the Verwaltungsgemeinschaft Habach (administrative community) are given a pre-subscription right. The municipalities of Obersöchering, Habach, Antdorf and Sindelsdorf can therefore subscribe in the first phase, within 14 days.
In the second phase, residents of the municipalities of the Verwaltungsgemeinschaft Seehausen a. Staffelsee, namely Riegsee, Seehausen a. Staffelsee and Spatzenhausen, can participate within a further 14 days.
It is possible to subscribe to a fixed-interest deposit. The interest rate is
4.0% per year over a term of 10 years. No closing fees apply for investors. The total deposit is limited to 5,000 euros per person. Deposits are possible from 500 euros up to 5,000 euros in steps of 50 euros.
Interest is paid on a repayment-in-instalments basis; this means that one tenth of the deposit is repaid each year. Interest is calculated solely on the amount not yet repaid.

| Term | Interest | Repayment | Interest date | Maturity |
|---|---|---|---|---|
| 10 years | 4.00 % p. a. | in equal instalments | 31.12. annually (first on 31.12.2026) | 31.12.2035 |
| Type of loan | in equal instalments |
|---|---|
| Interest payment frequency | annually |
| Available from | 07.07.2026 |
Downloads
Your personal payment plan (4.00 % interest p. a.)
| Year | Date | Payment (gross) | Interest | Repayment | Status |
|---|
Example calculation based on the terms, without accrued interest or a different first interest period; amounts rounded. Only the loan agreement and the investment information sheet (Vermögensanlagen-Informationsblatt) are authoritative. Taxes are not taken into account.