- Independence from external energy suppliers
- Combination of PV system and battery storage
- Construction and operation by a Stralsund company
Information for electricity customers of SWS Energie GmbH:
If you are an electricity customer of SWS Energie GmbH at the time of the annual interest payment on 30.09. of each year, you will receive an additional loyalty bonus of 0.50% p.a. on the subordinated loan amount outstanding at that time. You will receive these payments annually on 30.09. as a credit to your electricity customer account with SWS Energie GmbH. The loyalty bonus will be shown as a credit in the annual consumption statement for your electricity contract.
Welcome note


**Dear residents of Stralsund,
dear investors,
We, SWS Natur GmbH, are a 100% subsidiary of SWS Stadtwerke Stralsund GmbH. We would like to present our project for the construction and operation of a ground-mounted photovoltaic system in Stralsund. The solar park will be built within the urban area of the Hanseatic City of Stralsund, west of the Stralsund–Grimmen railway line. The land running parallel to the tracks belongs to the farmer Aurel Hagen, to the Landgesellschaft Mecklenburg-Vorpommern and, for the most part, to the Hanseatic City of Stralsund.
The project is another key building block for a green, regional and sustainable energy supply for the people of Stralsund and was developed by our project team. With this project, we won an award in the Federal Network Agency's innovation tender in April 2021. What makes this ground-mounted photovoltaic system special is its combination with a large battery storage system. The intelligent storage system serves to better integrate the new solar park into the Stralsund distribution grid.
For the implementation of the project we are supported by Dr. Metje Consulting GmbH, which has already successfully completed a large number of similar projects. Commissioning of the solar park is already planned for January 2023. 22,750 solar modules will then deliver an output of 10.46 megawatt peak. This will save 4,900 tonnes of CO2 per year and supply around 3,470 households with green electricity. The investment costs of 10.5 million euros secure CO2-neutral electricity production for the next 30 years and make their contribution to independence from the volatile electricity market.
The intervention in nature caused by constructing the system will be kept as low as possible, as compensation measures are planned. Our preferred option is to meet the compensation requirement with an extensively managed meadow or wildflower meadow.
If you would like to play an active part in shaping the energy transition and become part of this project, we would be delighted to have your participation!
Claas Möller and Harald Sauter**
Management of SWS Natur GmbH
Sunny prospects for the Hanseatic City of Stralsund
A ground-mounted photovoltaic system with an installed capacity of 10.46 MWp and a large battery storage system of 9 MWh is being built on a site of approx. 10 hectares in the Hanseatic City of Stralsund. 22,750 solar modules will generate around 10,400 MWh per year and supply 3,470 households with climate-neutral electricity. This can save 4,900 tonnes of carbon dioxide per year and significantly increase Stralsund's contribution to the energy transition.
An innovative solar park with large-scale storage is being built in Voigdehagen
Project
On the basis of its own land analysis in autumn 2020, the current 10-hectare project site was selected as a suitable location for the solar park. With the innovative concept of combining generation facilities with installations that absorb temporarily stored energy and convert it into electrical energy, SWS Natur GmbH took part in the Federal Network Agency's complex tender procedure at the beginning of April 2021. The award for a guaranteed remuneration was granted at the end of April 2021.
Since then, planning of the 10.46 megawatt peak solar park, including a storage system with a capacity of 3.8 megawatts, has been advanced intensively. In the third and fourth quarters of 2021, yield, soil, glare, and nature and species protection assessments were commissioned. At the end of January 2022, the EU tender for the construction of the solar park began; it was concluded at the beginning of April with the award to Dr. Metje Consulting GmbH. Thanks to the cooperative work of all parties involved, the long-awaited groundbreaking ceremony was able to take place on 12.04.2022. The first electricity is expected to be produced from January 2023.
Over the next 30 years, the system will generate green, regional and sustainable electricity for the people of Stralsund and further increase independence from the volatile electricity market. This can save 4,900 tonnes of CO2 per year and supply 3,470 households with green electricity.
Opportunities and risks
Opportunities:
SWS Natur GmbH as local developer and a 100% company of the Hanseatic City of Stralsund
Greater independence from the volatile electricity market
Guaranteed EEG remuneration for 20 years
Risks:
A possible risk of failure is covered by property insurance including loss-of-yield cover
The module manufacturer's performance guarantee rules out reduced module yield
Loss of the production site is ruled out by secured usage agreements for 25 + 5 years
Opportunities:
SWS Natur GmbH is the developer and owner of the solar park in the urban area of the Hanseatic City of Stralsund. SWS Stadtwerke Stralsund GmbH, as its sole shareholder, is a long-established company and enjoys great esteem and trust among the people of Stralsund. With these qualities, SWS Natur GmbH is ideally placed, as a regional company, to contribute to shaping the energy transition locally. Operating the solar park over the next 30 years will generate green, regional and sustainable electricity for the people of Stralsund and contribute to independence from the volatile electricity market. In addition, the system makes a significant contribution to the Hanseatic City of Stralsund's goal of covering its entire electricity demand from exclusively green self-generation from 2025. The EEG remuneration, secured for 20 years, also makes an essential contribution to the realisation of the solar park. This was secured by taking part in an innovation tender of the Federal Network Agency and the resulting award.
Risks:
One risk of the photovoltaic system would be a possible failure, as a result of which no revenue could be generated. As this risk is of great importance for the operation of the system, loss-of-yield cover was taken out as part of the property insurance. Another risk is a potential reduced yield of the modules. It would be possible, for example, for the delivered modules to have a lower output than contractually agreed. This would have a negative effect on the system's total forecast electricity yield. To counter this risk, a performance guarantee was obtained from the module manufacturer. A risk assessed as lower is the loss of the project site used, and thus also of the production site. For this reason, long-term usage agreements were concluded with all landowners. These provide for a contractual usage period of 25 years with an option to extend for a further five years. In total, the system can remain on the project site for 30 years.
Use of funds
To ensure the financing of the photovoltaic system, in addition to taking out a loan from DKB, crowdfunding is also being used. On the one hand, this makes it possible to provide 70% of the equity required for the project and, on the other, it enables the people of Stralsund to participate actively in the energy transition. The project is intended to contribute significantly to making the electricity supply of the Hanseatic City of Stralsund green, regional and sustainable. This offers considerable added value, in particular with regard to increasing independence from the volatile energy market.
Source of funds – financing structure
The total investment required to build the solar park is 10.55 million euros. 90% of this amount is financed through a DKB loan. The equity of one million euros will largely be provided via DKB-Crowd.

Project company
The owner of the photovoltaic system and the borrower is SWS Natur GmbH, a 100% subsidiary of SWS Stadtwerke Stralsund GmbH. SWS Natur GmbH was founded on 02.02.2012 and is registered with the Stralsund Local Court under HRB 8355. It is represented by its two managing directors, Claas Möller and Harald Sauter. The company focuses in particular on expanding the generation of renewable energy. This includes not only the four combined heat and power plants and the biogas plant, but also the construction and operation of photovoltaic systems on the roofs of Stralsund. Strong growth has been recorded in the field of solar energy since 2019. Through cooperation with the Office for Schools and Sport of the Hanseatic City of Stralsund, nurseries and schools in particular were fitted with rooftop systems during this period. Renewable energy is also generated on the roofs of the biogas plant site, the combined heat and power plants and regionally based companies.
Organisation chart

SWS Natur GmbH offers investors a subordinated loan with a total amount of 700,000 euros. This loan is an instalment loan with annual repayment and a term of seven years. The loan bears interest at 2% p.a. At the beginning of the investment period, owners of buildings in the heritage-protected area of Stralsund's old town, which forms part of the UNESCO World Heritage Site, will have priority access to this offer. Afterwards, all investors will be able to support the project.
The following table shows the financial plan for the photovoltaic system G9 in Voigdehagen.

Operating cash flow is determined by revenue. The guaranteed EEG remuneration secures low-risk and stable income over the next 20 years. Cash flow from financing activities consists of the debt funds used to finance the project and the resulting interest and repayment payments. In 2022, cash flow from investing activities is dominated by the construction of the solar park. No further investments are planned for this solar park in the years shown below.
In the following table, we present two example calculations.

The table considers two investment amounts at the project start on 20.07.2022. With an investment of 250 €, you receive an interest rate of 2%. You receive annual payments made up of repayment and interest. Repayment is 36 € per year over a term of seven years. In addition, there is interest, which at the start of the term is 6 €. In total, you earn 21 € over the term.
The second half of the table shows a calculation for an investment amount of 5,000 €. An interest rate of 2% is likewise applied here. For this amount, an annual repayment of 714 € is planned. Interest payments at the start of the term are 120 €. In total, with this option you earn 420 € over the term.
| Term | Interest | Repayment | Interest date | Maturity |
|---|---|---|---|---|
| 7 years | 2.00 % p. a. | Instalment loan | 30.09. annually (first on 30.09.2023) | 30.09.2029 |
| Type of loan | Instalment loan |
|---|---|
| Interest payment frequency | annually |
| Available from | 20.07.2022 |
| Minimum investment | EUR 250 |
| Maximum investment | EUR 5,000 |
Downloads
Your personal payment plan (2.00 % interest p. a.)
| Year | Date | Payment (gross) | Interest | Repayment | Status |
|---|
Example calculation based on the terms, without accrued interest or a different first interest period; amounts rounded. Only the loan agreement and the investment information sheet (Vermögensanlagen-Informationsblatt) are authoritative. Taxes are not taken into account.