- 100% municipally owned company
- Reliable heat supply for more than 60 years
- Investing in climate-neutral heat generation
Pre-subscription phase
From 01.07.2024 to 31.08.2024, the “Wärmespeicher” (heat storage facility) project is open exclusively to residents of Hennigsdorf (postcode 16761) and employees of Stadtwerke Hennigsdorf. Interest of 5.5% is paid. From 01.09.2024, the project is open to investors nationwide at 4.5%.
Welcome note

Dear investors,
I am delighted to present to you today a project that is of great importance not only for our town, but also for the sustainable development of our entire region.
For more than 60 years, Stadtwerke Hennigsdorf has been a reliable heat supplier for Hennigsdorf. It now supplies around 80 per cent of the Hennigsdorf urban area with district heating that is predominantly generated from renewable sources. This corresponds to about 12,000 households or 20,000 residents.
With the construction of a multifunctional heat storage facility in the north of Hennigsdorf, we are setting a new milestone on the path towards a climate-friendly heat supply in Hennigsdorf. With the heat storage facility, heat supply in Hennigsdorf will in future be more efficient, more sustainable and more independent. The heat storage facility also makes it possible to make greater use of the waste heat potential from the adjacent steel and rolling mill. The share of sustainably generated district heating can thus be increased from the current figure of around 60 per cent to up to 80 per cent.
Stadtwerke Hennigsdorf is a municipal company with deep roots in the local community. We support local clubs and projects and are actively committed to transforming our heat generation in order to significantly reduce CO2 emissions. This commitment to environmental protection and the common good is a core part of our corporate philosophy.
In an exclusive two-month pre-subscription phase, we are first offering the residents of Hennigsdorf and our employees the opportunity to subscribe to the subordinated loan, before subscription is then opened to all investors across Germany. We offer investors from Hennigsdorf an increased interest rate of 5.5 per cent per year. Investors from outside Hennigsdorf receive interest of 4.5 per cent per year. With an investment from EUR 250.00, we also want to give very small investors the opportunity to invest in this forward-looking project. The maximum investment amount is limited to EUR 25,000.00 per person.
I warmly invite you to become part of this important initiative. Your investment enables us to be a pioneer in sustainable energy supply and demonstrates your commitment to a more environmentally friendly future. Together we can make a significant difference – for our town, our environment and future generations.
With best wishes,
Christoph Schneider
Managing Director, Stadtwerke Hennigsdorf GmbH
Contribution to the UN Sustainable Development Goals
We care about our town and the region. That is why, through forward-looking investments, we want not only to help increase independence from fossil fuels, but also to ensure a sustainable, price-stable and reliable heat supply. With district heating, we do our part to keep the air clean in the town and the region. At the same time, we are increasing the energy sector's contribution to a climate-neutral municipality. In addition to the statutory requirements for achieving the 2045 climate targets, we are already trying today to reach this target voluntarily and significantly earlier. Sustainable heat supply avoids and minimises emissions, in particular CO2.
Opportunities and risks
| Opportunities | Risks |
|---|---|
|
|
Pioneering sustainable heat in Hennigsdorf: construction of an innovative heat storage facility:
By 2045, all German district heating suppliers must switch their energy supply to climate-neutral production. Stadtwerke Hennigsdorf has already come a long way on this path: our district heating network is already 60 per cent climate-friendly today – a figure that is well above the industry average. We are proud of this and now want to build on this success. With the planned construction of a large, multifunctional heat storage facility in the north of our town, directly next to the Hennigsdorf steel mill, we are taking a decisive step towards a fully sustainable heat supply.
Project details:
The heat storage facility will have a diameter of around 18 metres, a height of approximately 24 metres and a volume of around 5,100 cubic metres. This facility enables us to use the waste heat potential available at the neighbouring steel mill to an even greater extent. At present, this waste heat contributes almost 8,500 MWh per year to the energy mix. With the new heat storage facility, this figure will rise significantly, which will further reduce the share of fossil fuels in our heat generation.
Construction phase and schedule:
The building permit for the heat storage facility has been granted and construction work has already begun. The foundation was completed in February 2024. The construction of the outer shell is currently under way. Construction progress can be observed on site every day. Completion of the project is planned for September 2024, and filling will be completed by October 2024, so that operation can start in time for the 2024/2025 heating season.
Financing and investment opportunities:
The total investment costs for the heat storage facility amount to around EUR 5 million. Of this, EUR 1.3 million is provided through funding from the Federal Ministry for Economic Affairs and Climate Action under the federal funding for efficient heat networks. A further EUR 2.7 million will be provided by a bank loan and EUR 1 million from crowdfunding.
Community participation and image gain:
This project offers investors an excellent opportunity to take part directly in the heat transition and to benefit from an attractive interest rate. It also strengthens the image of Stadtwerke Hennigsdorf as a pioneer in sustainable energy supply, both locally and nationwide.
Aims and benefits:
Efficient use of heat: Storing heat enables a supply that is independent of energy generation. Surplus heat can be stored and released as needed, which is particularly advantageous during peak load periods in winter.
Integration of industrial waste heat: By extracting waste heat from the neighbouring steel and rolling mill, the share of sustainably generated district heating in Hennigsdorf will be increased from the current figure of around 60% to up to 80% in future.
Reduction of CO2 emissions: More effective use of waste heat and an increased share of renewable energy in the district heating system lead to a significant reduction in CO2 emissions.
Project company:
The project company is Stadtwerke Hennigsdorf GmbH – a municipal company whose shares are 100 per cent held by the town of Hennigsdorf. Stadtwerke Hennigsdorf GmbH was founded in 1990. With our Hennigsdorf district heating, we supply households, municipal facilities and commercial and industrial businesses. Our supply area covers around 80 per cent of the urban area.
As a municipal company, we feel a duty to the people of Hennigsdorf. Our commitment to Hennigsdorf goes beyond energy supply. We actively support local clubs and projects and thus help to strengthen the common good and improve quality of life in our town.
Ever since the district heating bylaw for Hennigsdorf came into force, we have been pursuing the goal of a climate-friendly heat supply for Hennigsdorf. On this path, a solar thermal system was already put into operation in 2001. An important milestone was the commissioning of our biomass combined heat and power plant in 2009, through which we reached a share of around 50 per cent sustainably generated heat for the first time. Further measures, such as the construction of a biogas combined heat and power unit in 2011 and the extraction of waste heat from the local steel and rolling mill since 2019, have increased the share of climate-friendly heat to around 60 per cent today.
In addition to district heating supply, we – also through our subsidiaries – provide various other services, which are primarily at municipal level.
**Organisation chart:

Use of funds:**
The crowdfunding is intended to raise an amount of up to EUR 1 million. The capital generated therefore reduces the equity requirement.
Source of funds – financing structure:
The total investment costs for the heat storage facility amount to around EUR 5 million. Of this, EUR 1.3 million is provided through funding from the Federal Ministry for Economic Affairs and Climate Action under the federal funding for efficient heat networks. A further EUR 2.7 million will be provided by a bank loan and EUR 1 million from crowdfunding.

Investors from Hennigsdorf and employees of the issuer receive annual interest of 5.5 per cent on the subordinated loan they have granted. All other investors receive annual interest of 4.5 per cent. Interest is paid once a year on the reference date of 30.06., for the first time on 30.06.2025. The subordinated loan is repaid in equal instalments over the total term of 10 years. This means that investors receive 10 per cent of the loan amount back together with the interest payment on 30.06. each year, for the first time on 30.06.2025.
The interest and repayments to be paid to investors are financed from the ongoing sales revenue of the district heating division.


| Term | Interest | Repayment | Interest date | Maturity |
|---|---|---|---|---|
| 10 years | 5.50 % p. a. | Instalment loan | 30.06. annually (first on 30.06.2025) | 30.06.2034 |
| Type of loan | Instalment loan |
|---|---|
| Interest payment frequency | annually |
| Available from | 01.07.2024 |
Downloads
Your personal payment plan (5.50 % interest p. a.)
| Year | Date | Payment (gross) | Interest | Repayment | Status |
|---|
Example calculation based on the terms, without accrued interest or a different first interest period; amounts rounded. Only the loan agreement and the investment information sheet (Vermögensanlagen-Informationsblatt) are authoritative. Taxes are not taken into account.