After a long planning phase, we are pleased that the history of wind energy in the municipality of Ihlow is entering a new phase for the first time. Wind turbines have been in operation in the Blitzniederung area between Riepe and Simonswolde since 1999. They have reached the end of their service life and will be replaced this year by new, state-of-the-art wind turbines.
It is the firm conviction of the operating company that the local population should also share in the value created by and from the operation of the wind turbines. In addition to its involvement in the Windkraft Ihlow Stiftung and the municipal participation under the Renewable Energy Sources Act (EEG), this offer also gives residents the opportunity both to support the project and to share in its success.
We have deliberately opted for an easily accessible, internet-based investment opportunity in order to reach as many interested people as possible.
We hope that the terms offered make this an attractive investment opportunity for you.
Contribution to the UN Sustainable Development Goals
High recyclability of the newly built wind turbines.
Production of CO2-neutral energy. Saving of 82,600 tonnes of CO2 p.a. compared with coal as an energy source.
Opportunities and risks
| Opportunities | Risks |
|---|---|
|
|
WPI Repowering GmbH & Co. KG took over from Windpark Ihlow GmbH & Co. Betriebs KG the project to carry out the repowering. Repowering means that existing wind turbines are dismantled and new, more powerful wind turbines are built in the same area.
The holder of the usage rights is and remains Windpark Ihlow GmbH & Co. Betriebs KG, which is also the owner of the infrastructure, consisting of private roads and cable systems.
During planning, the project company and the state road construction authority coordinated their respective plans for the area. The locations of the new wind turbines have been chosen so that, once the route has been optimised, the alignment of a planned federal road can be routed through the wind farm.
For the service life of the wind turbines, the project company will build and operate 14 ENERCON E-138 EP3 E2 turbines, each with a rated capacity of 4,200 KW and a hub height of 130.2 metres, which feed into AVACON's 110KV grid via an approx. 17km cable system and the Ihlow substation (EWE Netz GmbH).
To reduce night-time noise emissions, the project company operates the wind turbines during the night-time hours at a reduced output of max. 2,960 KW. The wind turbines will also be equipped with a legally required system for demand-controlled night-time marking, so that the obstruction lights on the wind turbines are only lit when needed, i.e. when an aircraft is nearby.
To protect military air safety, the wind turbines will also be equipped with a control system that enables the German armed forces (Bundeswehr) to briefly stop the wind turbines if necessary.
The wind turbines were approved on 25.07.2022 under the Federal Immission Control Act. In October 2022, the project company received awards for all wind turbines in the tender procedure under the EEG, which secures a minimum remuneration of 58.20 €/MWh to 58.60 €/MWh for 20 years of operation. The average is 58.40 €/MWh. The quality of the site affects the applicable value of the remuneration via the determination of the correction factor. The correction factor is initially determined by expert assessment and its accuracy is reviewed retrospectively every five years of operation. For the first five years of operation, the average quality factor is 78.77 % (P-75 value), resulting in a correction factor of 1.18 and an applicable value of 69.00 €/MWh (average).
On average, the wind turbines produce approx. 10,353 MWh p.a. (P-75 value), so the calculation is based on an annual energy output of 144,942 MWh.
Development work began in spring 2023. The foundations of the wind turbines were built from September 2023. The wind turbines have been under construction since January 2024. Eight wind turbines are currently in operation. The remaining six wind turbines are scheduled to be commissioned at the beginning of October 2024.
Use of funds
The capital will be used to invest in 14 wind turbines from the manufacturer ENERCON, type E-138 EP3 E2 with a hub height of 130.2m and a rated capacity of 4,200 KW, together with infrastructure, permit fees, pre-financing costs, grid connection, and project planning and expert assessment costs.
Source of funds – financing structure

Project company
The project company consists of individual investors, landowners, a community wind farm company and a subsidiary of Alterric GmbH. No shareholder holds more than 50% of the shares. The general partner with personal liability is Windpark Ihlow Verwaltungs-GmbH.
Subordinated loans are offered to a qualified group of persons. The investment amount is limited to 15,000 € per investor.
The investor grants the issuer a loan with bullet repayment at maturity and a maximum term of 15 years. For the term of the loan, the issuer pays interest at a rate of 6.5% p.a. The loan principal is repaid at the end of the loan.
| Term | Interest | Repayment | Interest date | Maturity |
|---|---|---|---|---|
| 15 years | 6.50 % p. a. | bullet repayment at maturity | 31.12. annually (first on 31.12.2024) | 31.12.2039 |
| Type of loan | loan with bullet repayment at maturity |
|---|---|
| Interest payment frequency | annually |
| Available from | 01.10.2024 |
| Minimum investment | EUR 1,000 |
| Maximum investment | EUR 15,000 |
Downloads
Your personal payment plan (6.50 % interest p. a.)
| Year | Date | Payment (gross) | Interest | Repayment | Status |
|---|
Example calculation based on the terms, without accrued interest or a different first interest period; amounts rounded. Only the loan agreement and the investment information sheet (Vermögensanlagen-Informationsblatt) are authoritative. Taxes are not taken into account.